The Project: A Milestone for Kolkata's Purple Line
In August 2026, Kolkata Metro's Purple Line achieved a major construction milestone. Tunnel Boring Machine "Divya" completed its drive between Khidderpore and Victoria stations — a stretch of roughly 1.72 km through some of Kolkata's most challenging soil, dense with groundwater and packed with existing infrastructure overhead. Its sister machine, "Durga," had broken through the same section a few weeks earlier. Together, the two drives completed the twin-tunnel connection for this segment of the Joka–Esplanade corridor, one of the most closely watched underground rail projects in eastern India, executed by RVNL with L&T as the contracting agency.
A TBM breakthrough is a highly technical moment. Long before the machine reaches its target, a precise opening has to be cut into the receiving shaft's concrete wall — sized, positioned, and finished to exact tolerances so the machine can emerge without damaging the structure around it or compromising the surrounding soil. This is where specialized concrete cutting comes in — and where Armatix's team was engaged.
Armatix's Role: Stitch Core Cutting an 8.6m Opening
For this project, the requirement was to create a circular opening 8.6 metres in diameter through heavily reinforced concrete — far beyond what a conventional wall saw or single-pass core drill can handle. Armatix approached it using stitch core cutting, executed as follows:
- The opening was divided into 8 equal segments, each planned around the full 8.6m circumference.
- A series of closely spaced diamond core holes was drilled along the cut line of each segment, so adjacent holes overlapped enough to form a continuous, controlled separation line — essentially "stitching" through the concrete core by core.
- Each segment was then broken out and removed individually, rather than attempting to free the entire 8.6m disc in one piece — reducing load, vibration, and risk to the surrounding shaft structure.
- Reinforcement bars encountered along the cut line were cut clean by the diamond core bits themselves, avoiding the impact and vibration that a hydraulic breaker or conventional demolition method would introduce.
The result: a precisely sized opening, cut without cracking, over-break, or vibration damage to the shaft lining — clearing the exact path the TBM needed to pass through safely.